Define a comparable starting point
Hold scope, calendars and baseline conditions constant across options. Identify exactly which supplier, resource or sequence assumptions change.
Compare delivery responses with their time, cost and execution assumptions in view.
Request a QuoteSwitchgear delivery moves seven working days. With no spare float on this simplified chain, installation, energization and testing all move seven days.
Exposure assumes $18,000 per additional working day plus the stated intervention cost. This simplified model is not a validated prediction.
Teams need to evaluate more than one revised completion date. Sorqis helps teams compare schedule recovery options, resource alternatives and procurement responses against the same project context.
Workflows designed to support the professionals responsible for delivery.
Hold scope, calendars and baseline conditions constant across options. Identify exactly which supplier, resource or sequence assumptions change.
Explore resequencing, crew allocation or procurement recovery while retaining physical dependencies. Do not assume that parallel execution is possible merely because a bar can move.
Show schedule movement, modeled cost exposure and remaining uncertainty together. Record who accepted the assumptions and what evidence would trigger another review.
Compare a seven-day supplier delay with a partial recovery that reduces it to three days at an assumed $45,000 expediting cost. These inputs produce four recovered working days; feasibility depends on supplier capacity, site readiness and the agreed execution sequence.
Support structured option reviews with transparent tradeoffs. Scenario outputs describe consequences of assumptions; they do not guarantee future outcomes.
Agree the scope, data requirements, analytical methods and reporting deliverables before your engagement begins.