05 / Test the alternatives

Explore the decision before you commit.

Compare delivery responses with their time, cost and execution assumptions in view.

Request a Quote
Construction risk intelligence, scoped around your project requirements.
SCENARIO COMPLETION / WORKING DAYS FROM 02 NOV 2026
Baseline
30d
$0
Supplier delay
37d
$126,000
Resource constraint
35d
$90,000
Mitigation
33d
$99,000

Late switchgear delivery

Switchgear delivery moves seven working days. With no spare float on this simplified chain, installation, energization and testing all move seven days.

Exposure assumes $18,000 per additional working day plus the stated intervention cost. This simplified model is not a validated prediction.

The delivery challenge

A recovery plan is only useful when its tradeoffs are understood.

Teams need to evaluate more than one revised completion date. Sorqis helps teams compare schedule recovery options, resource alternatives and procurement responses against the same project context.

01 / CONNECTED INPUTS

Bring the right
signals together.

  • Current schedule and accepted baseline
  • Alternative resource assignments and working patterns
  • Procurement recovery options and revised sequences
  • Cost rates, access restrictions and approval constraints
02 / EMERGING EXPOSURE

Know where
to look closer.

  • Completion-date changes under explicit assumptions
  • Time-versus-cost tradeoffs across alternatives
  • Transferred risk between work packages
  • Constraints that make a recovery option impractical
A practical intelligence workflow

From observation to understanding.

Workflows designed to support the professionals responsible for delivery.

01

Define a comparable starting point

Hold scope, calendars and baseline conditions constant across options. Identify exactly which supplier, resource or sequence assumptions change.

02

Test a feasible intervention

Explore resequencing, crew allocation or procurement recovery while retaining physical dependencies. Do not assume that parallel execution is possible merely because a bar can move.

03

Make the decision reviewable

Show schedule movement, modeled cost exposure and remaining uncertainty together. Record who accepted the assumptions and what evidence would trigger another review.

A construction example

Follow the consequence.

Compare a seven-day supplier delay with a partial recovery that reduces it to three days at an assumed $45,000 expediting cost. These inputs produce four recovered working days; feasibility depends on supplier capacity, site readiness and the agreed execution sequence.

SCHEDULE LOGIC · COST ASSUMPTIONS · PROJECT IMPACT
Value for your team

Clarity that supports
better judgment.

Support structured option reviews with transparent tradeoffs. Scenario outputs describe consequences of assumptions; they do not guarantee future outcomes.

Agree the scope, data requirements, analytical methods and reporting deliverables before your engagement begins.

A clearer picture starts here

Bring your next
project into focus.

Let’s discuss your project controls challenges
and where connected intelligence could help.

Request a QuoteStart a conversation Built for the complexity of construction.