04 / Read the rate of progress

Understand the work behind the percentage.

Connect measured output, labor effort and resource capacity to credible remaining durations.

Request a Quote
Construction risk intelligence, scoped around your project requirements.
WORK PACKAGE / CABLE ROUTESProduction rate calculator

The same scope.
A different finish.

Remaining quantity480m
Estimated duration15working days
Baseline variance+3days
20 M / DAYBASELINE: 40 M / DAY60 M / DAY

Duration = remaining quantity ÷ daily production, rounded up to a full working day. Assumes comparable scope, a stable crew and uninterrupted access. Additional labor does not necessarily increase the production rate.

The delivery challenge

A reported percentage complete does not explain whether the remaining work can finish on time.

Aggregate progress can mask uneven production rates across work fronts. Sorqis helps teams examine quantities installed, hours worked and available capacity, making resource-related schedule exposure easier to investigate.

01 / CONNECTED INPUTS

Bring the right
signals together.

  • Planned and installed quantities by work package
  • Labor hours, crew composition and working calendars
  • Resource availability and work-front readiness
  • Baseline production rates and remaining quantities
02 / EMERGING EXPOSURE

Know where
to look closer.

  • Planned versus actual output and productivity variance
  • Production trends that imply longer remaining duration
  • Workforce bottlenecks and competing resource demands
  • Resource exposure linked to schedule dependencies
A practical intelligence workflow

From observation to understanding.

Workflows designed to support the professionals responsible for delivery.

01

Measure comparable work

Align quantities and labor effort to the same work package and period. Treat missing timesheets, rework and measurement changes as data quality issues before drawing conclusions.

02

Distinguish rate from capacity

A productive crew may still lack sufficient capacity. Compare output per labor hour with total available hours to identify whether the issue is efficiency, staffing or access.

03

Reassess the remaining duration

Estimate how long remaining quantities may take at observed rates. Test whether additional resources are feasible given supervision, congestion and work-front availability.

A construction example

Follow the consequence.

A work package with 480 meters remaining requires 12 working days at 40 meters per day. At 32 meters per day it requires 15 days, assuming a stable crew, comparable scope and uninterrupted access.

SCHEDULE LOGIC · COST ASSUMPTIONS · PROJECT IMPACT
Value for your team

Clarity that supports
better judgment.

Give planning and site teams an explicit basis for discussing production recovery without assuming that additional labor automatically increases output.

Agree the scope, data requirements, analytical methods and reporting deliverables before your engagement begins.

A clearer picture starts here

Bring your next
project into focus.

Let’s discuss your project controls challenges
and where connected intelligence could help.

Request a QuoteStart a conversation Built for the complexity of construction.