Measure comparable work
Align quantities and labor effort to the same work package and period. Treat missing timesheets, rework and measurement changes as data quality issues before drawing conclusions.
Connect measured output, labor effort and resource capacity to credible remaining durations.
Request a QuoteDuration = remaining quantity ÷ daily production, rounded up to a full working day. Assumes comparable scope, a stable crew and uninterrupted access. Additional labor does not necessarily increase the production rate.
Aggregate progress can mask uneven production rates across work fronts. Sorqis helps teams examine quantities installed, hours worked and available capacity, making resource-related schedule exposure easier to investigate.
Workflows designed to support the professionals responsible for delivery.
Align quantities and labor effort to the same work package and period. Treat missing timesheets, rework and measurement changes as data quality issues before drawing conclusions.
A productive crew may still lack sufficient capacity. Compare output per labor hour with total available hours to identify whether the issue is efficiency, staffing or access.
Estimate how long remaining quantities may take at observed rates. Test whether additional resources are feasible given supervision, congestion and work-front availability.
A work package with 480 meters remaining requires 12 working days at 40 meters per day. At 32 meters per day it requires 15 days, assuming a stable crew, comparable scope and uninterrupted access.
Give planning and site teams an explicit basis for discussing production recovery without assuming that additional labor automatically increases output.
Agree the scope, data requirements, analytical methods and reporting deliverables before your engagement begins.