Make the comparison meaningful
Align cost codes, reporting periods and approved scope. Separate a timing difference from a permanent change in expected outturn cost.
Bring cost variance, productivity and delivery conditions into the same analytical view.
Request a QuoteSelect a period to inspect cumulative cost variance. Positive variance means actual cost exceeds planned cost. This is not earned-value cost variance; scope and progress must be assessed separately.
Cost reporting often arrives after the operational conditions that created the variance. Sorqis helps teams connect financial information to schedule movement and production performance, helping teams distinguish booked costs from emerging exposure.
Workflows designed to support the professionals responsible for delivery.
Align cost codes, reporting periods and approved scope. Separate a timing difference from a permanent change in expected outturn cost.
Relate unfavorable production rates and prolonged site overhead to the activities that generate them. Avoid treating every schedule delay as an equal financial impact.
Compare estimate-at-completion assumptions, remaining quantities and contingency use. Make exclusions and uncertainty visible alongside the forecast.
Seven additional working days at an assumed site overhead of $18,000 per day create $126,000 of time-related exposure. This excludes escalation, liquidated damages and subcontractor claims.
Help commercial and project controls teams examine potential exposure before it appears in the final account. Financial illustrations are analytical examples, not savings commitments.
Agree the scope, data requirements, analytical methods and reporting deliverables before your engagement begins.