Connect packages to the programme
Map each critical package to its required-on-site milestone and dependent activities. Retain intermediate approval and fabrication steps so the delivery date has a traceable basis.
Understand how materials, equipment and supplier commitments connect to construction readiness.
Request a QuoteScenario supplier commitment moves from day 10 to day 17. Seven days of delay propagate through the zero-float installation chain.
A procurement register can show delivery dates without revealing which construction activities depend on them. Sorqis helps teams map long-lead packages to installation, testing and commissioning milestones.
Workflows designed to support the professionals responsible for delivery.
Map each critical package to its required-on-site milestone and dependent activities. Retain intermediate approval and fabrication steps so the delivery date has a traceable basis.
Assess delivery variance against schedule float and available alternatives. A small variance on a critical package may deserve more attention than a larger variance on a noncritical order.
Examine phased delivery, alternative sequencing or expediting. Identify the approvals, additional costs and installation constraints required for each response.
Switchgear arrives seven working days late. Installation cannot begin, energization slips and integrated systems testing moves. Expediting the final shipment may help only if the receiving area and installation crew are ready.
Support coordination between procurement, site teams and project controls using a shared account of delivery consequence.
Agree the scope, data requirements, analytical methods and reporting deliverables before your engagement begins.