03 / Follow the dependencies

A late delivery is rarely just a late delivery.

Understand how materials, equipment and supplier commitments connect to construction readiness.

Request a Quote
Construction risk intelligence, scoped around your project requirements.
PACKAGE SG-01 / SWITCHGEARProcurement dependencies
SELECTED DEPENDENCY

Equipment delivery

Scenario supplier commitment moves from day 10 to day 17. Seven days of delay propagate through the zero-float installation chain.

The delivery challenge

Track the relationship between what is arriving and what the project needs to do next.

A procurement register can show delivery dates without revealing which construction activities depend on them. Sorqis helps teams map long-lead packages to installation, testing and commissioning milestones.

01 / CONNECTED INPUTS

Bring the right
signals together.

  • Equipment and material procurement registers
  • Required-on-site dates and supplier commitments
  • Design approvals, fabrication and shipping milestones
  • Linked installation and commissioning activities
02 / EMERGING EXPOSURE

Know where
to look closer.

  • Long-lead items approaching available float limits
  • Changes in supplier commitments and missing updates
  • Construction work fronts exposed to late delivery
  • Downstream effects on testing and handover sequences
A practical intelligence workflow

From observation to understanding.

Workflows designed to support the professionals responsible for delivery.

01

Connect packages to the programme

Map each critical package to its required-on-site milestone and dependent activities. Retain intermediate approval and fabrication steps so the delivery date has a traceable basis.

02

Prioritize by consequence

Assess delivery variance against schedule float and available alternatives. A small variance on a critical package may deserve more attention than a larger variance on a noncritical order.

03

Evaluate practical recovery

Examine phased delivery, alternative sequencing or expediting. Identify the approvals, additional costs and installation constraints required for each response.

A construction example

Follow the consequence.

Switchgear arrives seven working days late. Installation cannot begin, energization slips and integrated systems testing moves. Expediting the final shipment may help only if the receiving area and installation crew are ready.

SCHEDULE LOGIC · COST ASSUMPTIONS · PROJECT IMPACT
Value for your team

Clarity that supports
better judgment.

Support coordination between procurement, site teams and project controls using a shared account of delivery consequence.

Agree the scope, data requirements, analytical methods and reporting deliverables before your engagement begins.

A clearer picture starts here

Bring your next
project into focus.

Let’s discuss your project controls challenges
and where connected intelligence could help.

Request a QuoteStart a conversation Built for the complexity of construction.